22 Aug 2018 / Singapore
The working period for work to remove a jetty and install mono piles at Pulau Seborok has been extended.
According the Maritime and Port Authority of Singapore Port Marine Notice No.085 of 2018, the works are being conducted 24 hours daily - including Sundays & Public Holidays – from 23 August 2018 until 22 February 2019 within the working area bounded by the following coordinates (WGS 84 Datum):
1) 01 deg. 12.497'N / 103 deg. 47.728'E
2) 01 deg. 12.528'N / 103 deg. 47.779'E
3) 01 deg. 12.410'N / 103 deg. 47.892'E
4) 01 deg. 12.368'N / 103 deg. 47.852'E
Crane barges will be used in the removal and installation work. Diving operations will be performed as part of the monopile removal process.
Craft involved in the works will exhibit the appropriate local and international day and night signals.
When in the vicinity of the working area, mariners are reminded to:
a) Keep well clear and not to enter the working area;
b) Maintain a proper lookout;
c) Proceed at a safe speed and navigate with caution;
d) Maintain a listening watch on VHF Channel 68 (Western Control);
and
e) Communicate with Western Control on VHF Channel 68 for assistance, if required.
For information about operations in Singapore contact GAC Singapore at [email protected]
You are currently on GAC Worldwide website.
GAC Netherlands Rotterdam Main Office Mercuriusstraat 44
Group Vice President, Europe and Africa
16200 Central Green Blvd
78 Shenton Way #09-01 Singapore 079120
GAC Netherlands Rotterdam Main Office Mercuriusstraat 44
Group Vice President, Europe and Africa
Unit OT 18-35, Level 18, Central Park Towers, Dubai International Financial Centre, Dubai, P.O. Box 18006, United Arab Emirates
Leverage on our experience and expertise with integrated shipping, logistics and marine services tailored to meet your needs.