29 Sep 2015 / Singapore
The working period for reclamation work at Tuas View, off Temasek Fairway, has been extended. The work will now be carried out from 1 October 2015 to 30 April 2016.
As stated in the Maritime and Port Authority of Singapore Port Marine Notice No.112 of 2015 the works will be conducted 24 hours daily – including Sundays and public holidays – within the working area bounded by the following coordinates (WGS 84 Datum):
1) 01 deg. 16.297'N / 103 deg. 38.387'E
2) 01 deg. 16.297'N / 103 deg. 38.709'E
3) 01 deg. 15.415'N / 103 deg. 38.709'E
4) 01 deg. 15.415'N / 103 deg. 37.255'E
The reclamation work involves the removal of existing stone shore protection, dredging and underwater blasting at basin and sand key trench.
Craft involved in the works will exhibit the appropriate local and international day and night signals.
When in the vicinity of the working area, mariners are reminded to:
a) Keep well clear and not to enter the working area;
b) Maintain a proper lookout;
c) Proceed at a safe speed and navigate with caution;
d) Maintain a listening watch on VHF Channel 22 (Jurong Control);
and
e) Communicate with Jurong Control on VHF Channel 22 for assistance, if required.
For information about operations in Singapore contact GAC Singapore at [email protected]
You are currently on GAC Worldwide website.
Group Vice President, Europe and Africa
16200 Central Green Blvd
78 Shenton Way #09-01 Singapore 079120
Group Vice President, Europe and Africa
Unit OT 18-35, Level 18, Central Park Towers, Dubai International Financial Centre, Dubai, P.O. Box 18006, United Arab Emirates
Leverage on our experience and expertise with integrated shipping, logistics and marine services tailored to meet your needs.