Jetty Strengthening work at SWB

29 May 2025 / Nhava Sheva, India

Nhava Sheva Distribution Terminal Private Limited has advised that the third phase of jetty strengthening work at the SWB is expected to be completed by this Saturday, 31 May.

To ensure a smooth transition into the fourth and last phase, the last sequence of tasks is scheduled to begin immediately following the completion. This will take approximately two months and should be completed by the end of July 2025.

During this final phase of work, only vessels with LOA up to 130 metres will be accommodated, subject to the prevailing weather conditions.