Berth strengthening work complete

04 Aug 2025 / Jawaharlal Nehru Port, India

The strengthening work of the Shallow Water Berth of Nhava Sheva Distribution Terminal has been successfully completed.

The facility is now equipped and strengthened to accommodate vessels up to 45,000 MT displacement and a maximum LOA of 197.00 metres.

During this period, vessels up to 200 metres could be accepted subject to fair weather conditions and approval from the Port Authority’s Marine Department on a case-to-case basis.

The terminal now offers enhanced safety with upgraded new fenders and advanced berthing aids. Other berthing parameters continue to remain the same.