Shutdown of berths

16 Jun 2022 / Haldia, India

The ongoing shutdown works at HOJ-11 [Berth No.17(O)] are likely to be completed on 19 June and thus HOJ-11 in all probability will be available for vessel operation w.e.f. 20 June 2022.

Earlier, this office had intimated that the HOJ-1 [Berth No.16(O)] will remain under maintenance from 25 June for a period of 45 days. However, it has now been decided that the HOJ-1 [Berth No.16(O)] will remain under shutdown from 30 June to 17 August.

(For information about operations in India, contact GAC India at [email protected])

Source: Haldia Port Trust Trade Circular No.GMT/45/1148 dated 16 June 2022